Construction draw schedule template

How to use

Use this template before signing the construction loan documents to design the line-item draw schedule. The schedule is the operating contract between sponsor, GC, and lender for the next 24 months, designing it deliberately at closing eliminates 90% of mid-build draw friction.

Section 1, line-item structure

Mirror the GC's AIA G703 schedule of values exactly. Every line in the loan budget should match a line in the GC contract. Mismatches at the line-item level cause disputes at every monthly draw.

  • Hard-cost line items (per AIA G703, site, structure, MEP, finishes, GC fee, GC general conditions).
  • Soft-cost line items (architecture, MEP engineering, civil, environmental, permits, legal, financing, insurance, taxes, marketing, lease-up).
  • Hard-cost contingency (sized 5%-10% of hard costs based on project complexity).
  • Soft-cost contingency (sized 3%-5% of soft costs).
  • Interest reserve (sized to projected debt service through substantial completion plus stabilization buffer).
  • Operating-deficit reserve (for lease-up debt service shortfalls if not covered by interest reserve).

Section 2, retainage logic

Standard institutional retainage is 10% of each hard-cost line. Negotiate stepped retainage (10% on first 50%, then 5%) at term sheet, meaningful sponsor working-capital benefit on a long build.

  • Retainage rate (10% standard; stepped to 5% after 50% complete is sponsor-friendly).
  • Retainage release at substantial completion (typically half of held retainage; balance held to final completion).
  • Final retainage release at completion of punch list and delivery of unconditional final lien waivers.
  • Coordinate retainage between loan documents and GC contract to avoid mismatches.

Section 3, lien-waiver exchange cycle

Each draw cycle exchanges conditional waivers for the current draw against unconditional waivers for the prior draw. This is the four-form mechanic that handles the timing gap between billing and payment.

  • Current draw: GC and major subs deliver conditional progress waivers covering current draw amount.
  • Prior period: GC and same parties deliver unconditional progress waivers for prior period (now-paid).
  • Tracking: maintain a draw-by-draw waiver log keyed by sub and amount; verify completeness before submitting draw request.
  • Final completion: unconditional final waivers from GC and all known subs; lien-free completion certificate from title.

Section 4, stored-materials funding

Long-lead items (switchgear, elevators, HVAC, custom millwork) often require purchase 6 to 12 months before installation. Stored-materials funding lets the sponsor pay for them without funding out of equity.

  • On-site stored materials: typically funded at 100% of invoice with on-site verification.
  • Off-site stored materials at bonded supplier: typically funded at 80%-100% of invoice with bond + insurance + identification.
  • Funding cap (often $1M-$5M of stored materials per cycle; negotiable based on project complexity).
  • Insurance: stored materials must be insured by the supplier or sponsor; loss-payable to lender.

Section 5, lender-inspector cadence

Lender inspector visits the site before each monthly draw to validate percent-complete claims against AIA G702/G703.

  • Standard cadence: monthly inspector visits with 5- to 10-day reporting turnaround.
  • Sponsor-friendly tweak: quarterly inspector visits during defined low-risk periods (interior buildout, finishes).
  • Inspector report drives lender funding decision; disputes resolved by lender PM with escalation to senior credit if material.
  • Pre-draw coordination call (sponsor, GC, lender PM, inspector) eliminates 90% of friction.

Sample 24-month draw schedule cadence

PhaseDurationDrawsNotes
Mobilization + site workMonths 1-33 monthly drawsHeavier early on contingency review
StructureMonths 4-96 monthly drawsLargest dollar volume; tightest inspector cadence
MEP rough-inMonths 10-145 monthly drawsLong-lead stored materials hit here
Finishes + close-outMonths 15-228 monthly drawsPunch list begins; substantial completion target
Punch + finalMonths 23-242 final drawsFinal retainage release at lien-free certificate

Section 6, change-order process

Most loan documents require lender consent for change orders above a defined threshold (often $50K-$100K individual or $500K aggregate). Smaller changes flow through contingency without lender consent.

  • Threshold for individual change order requiring lender consent (typically $50K-$100K).
  • Aggregate threshold for cumulative change orders (typically $500K-$1M).
  • Documentation: GC change-order form, AIA G701, supporting cost backup, schedule impact analysis.
  • Approval timeline: typically 5-10 business days; expedited for time-sensitive items.
  • Funding: contingency-funded changes draw against contingency line; sponsor-funded changes via balancing test.